| Client | Major Iron Ore Client |
|---|---|
| Project Location | Pilbara, Western Australia |
| Project Value | $3,000,000 |
| Completion Time Frame | 26 weeks |
Scope of Work
- Design, engineer and construct 19 kiosk substations
- Kiosks Included 33kV 8DJH 33kV Switchgear, Remote Operations L&SP, Protection Relays.– all testing, pre-commissioning and FAT
- Functional Testing, OEM wiring of switchgear
- Project drawings including single line diagrams, schematics, termination, earthing, layout and general arrangements
- Project management of contractors – Surge Engineering, Siemens
- Delivery to site